ContactGreg Massey, PE Client/ReferenceDebbie Miller LocationOklahoma City, OK |
||
Project DescriptionThis project consisted of the evaluation of a 90 acre watershed that experienced heavy flooding in the area of SW 15th & McKinley Ave. The areas had existing storm sewer from the 1950’s that had failed. The existing storm sewer was found to have been discharging into a sanitary sewer manhole that was silted in. The improvements included reconstructing and extending the storm sewer to an existing earthen channel. The channel was reconfigured to accommodate the increased flow. |
Services Provided |